    When you need 3 to 6 people each day to help the main construction crew, the amount of volunteer time really adds up. Through 3 weekends of work we have had 21 different folks working, for a total of 38 days on the project. Thank you Steve, Rick, RB, Beth, Colin, Kasey, Steve, Alan, Sandy, Stu, Jeff, Al, Andrew, Marilyn, Samantha, Tom, Atticus, Brad, Dave, & Bonnie for all of your efforts!

    For the coming 4-day weekend (11/10-11/13), we could at least 3 people per day. I hope to see some of you at Madison Blue Springs this weekend.

    Mike


  2. #12
    Moderator
    Join Date
    Mar 2008
    Location
    Melbourne, FL
    Age
    70
    Posts
    1,885

    Default

    It's killing me I cannot come up and contribute. My drill batteries are charged, my tools are ready, but I am having a hard time justifying the total drive time against my current value to the project.

    Knee surgery last week still has me pretty limited...

    Life moves pretty fast. If you don't stop and look around once in a while, you could miss it.
    -Ferris Bueller

    The most certain way to stumble into the future, is to live your life looking over your shoulder.
    -Jeff Hawes after getting a huge mulligan...

  3. #13
    Member
    Join Date
    Mar 2006
    Location
    Moultrie, Georgia
    Posts
    1,679

    Default

    Thanks Jeff - your knee is not worth the risk. we will be there for a few more weeks just in case your knee allows it.

    Safe diving,

    Sandy Robinson

  4. #14
    Member
    Join Date
    Dec 2015
    Location
    Luraville
    Posts
    48

    Default

    We have a couple of folks helping on Sunday. It sure would be nice to get some additional help for Friday or Saturday. Call or text me at 850-728-0098 if you think you could help. No construction skills needed.
    Mike


  5. #15
    Member
    Join Date
    Dec 2015
    Location
    Luraville
    Posts
    48

    Default

    We will be at it again this weekend (11/19-20), and could use some more help.
    Mike


  6. #16
    Moderator
    Join Date
    Mar 2008
    Location
    Melbourne, FL
    Age
    70
    Posts
    1,885

    Default

    Curious, what is the status of the steps? Still looking for help or have I missed out?

    Life moves pretty fast. If you don't stop and look around once in a while, you could miss it.
    -Ferris Bueller

    The most certain way to stumble into the future, is to live your life looking over your shoulder.
    -Jeff Hawes after getting a huge mulligan...

  7. #17
    Member
    Join Date
    Jul 2014
    Location
    High Springs
    Posts
    620

    Default

    I just heard back from Mike, work on Martz will resume this Saturday. (Probably Sunday too, but I can't confirm that)


  8. #18
    Member
    Join Date
    Dec 2015
    Location
    Luraville
    Posts
    48

    Default

    Yes, we worked on Saturday and will be working again on Sunday 12/4.
    Mike


  9. #19
    Member
    Join Date
    Nov 2004
    Location
    Jacksonville, FL
    Posts
    2,305

    Default

    My wife and I had the privileged of joining the team working on the Martz steps project today and they are nearly finsihed! A solid day or two next weekend and it should be complete. We were very impressed to see all of the hard work that has gone into this project from the volunteers thus far. It is a fantastic addition to the park and will make diving Martz much easier, and better yet, safer! Today the team finished all railings on the upper level deck/walk way, benches and tank rack on the upper deck, posts and decking on the mid-level deck (this space/deck is new compared to the old setup... a bonus!) and about 1/2 of the railings down to the water. All that remains is the railings around the mid-level deck and final touches on the railings down to the water.


  10. #20
    Moderator
    Join Date
    Oct 2004
    Location
    south Georgia
    Posts
    7,398

    Default

    Quote Originally Posted by IowaCaveDiver View Post
    My wife and I had the privileged of joining the team working on the Martz steps project today and they are nearly finsihed! A solid day or two next weekend and it should be complete. We were very impressed to see all of the hard work that has gone into this project from the volunteers thus far. It is a fantastic addition to the park and will make diving Martz much easier, and better yet, safer! Today the team finished all railings on the upper level deck/walk way, benches and tank rack on the upper deck, posts and decking on the mid-level deck (this space/deck is new compared to the old setup... a bonus!) and about 1/2 of the railings down to the water. All that remains is the railings around the mid-level deck and final touches on the railings down to the water.
    The additions and changes are a vast improvement compared to what was there. Thank you and all the volunteers have been able to provide labor, and thank you again to all the monetary donations the project received.

    "Not all change is improvement...but all improvement is change" Donald Berwick


 

Similar Threads

  1. Martz Steps Construction Starts October 15
    By NFSA in forum Main Forum
    Replies: 2
    Last Post: 10-13-2016, 05:11 AM
  2. Martz steps
    By cmint in forum Main Forum
    Replies: 3
    Last Post: 12-19-2015, 11:03 PM
  3. Madison - Martz only
    By scottj in forum Dive Reports
    Replies: 6
    Last Post: 02-19-2013, 06:23 AM
  4. Frank Martz
    By Jay in forum Main Forum
    Replies: 32
    Last Post: 01-11-2007, 09:56 PM
  5. Emerald Steps update
    By Kelly Jessop in forum Main Forum
    Replies: 10
    Last Post: 08-03-2006, 07:11 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts